IMPROVING CONDITIONS FOR SOLAR ENERGY INVESTMENTS IN ETHIOPIA

By Kieran Whyte, Partner and Head of the Energy, Mining & Infrastructure Practice, Mike Webb, Senior Associate, Baker McKenzie Johannesburg, and Yibeltal Shiferaw, on secondment from Tadesse Kiros Law Offices (TKLO) in Ethiopia

Ethiopia are preparing for the future through its Solar Energy Investments. Solar Energy is one of the cleanest sources of energy available to humanity; especially in Africa where sunlight is abundant. African Nations are currently combining a number of energy mixes in order to meet energy demands and also bridge the continent’s infrastructure deficit which has power deficiency as on of its element.

Ethiopia Solar Energy Investments

The Ethiopian Government recently announced the commencement of a tender for four(4) solar photovoltaic (PV) projects. These four projects are in addition to two (2) Scaling Solar projects which are currently already under the IFC’s Scaling Solar Programme. In addition, two separate solar PV projects are also to commence later in the year. Each of these projects will be on a public private partnership (PPP) basis.

The request for proposals (RFPs) for the four projects will begin in late April or early May 2019. While the RFP for the two Scaling Solar projects will also be open for prequalified developers before the end of February this year. The term of the power purchase agreements (PPA) will be 20 years.

The below table summarizes the eight pending solar PV projects in Ethiopia:

No. Project Name Capacity (MW) Estimated Project Cost (USD Million) Region Status
1 Gad Solar Scale (Phase I) 125 150 Somali Scaling Solar
2 Dicheto Solar Scale (Phase I) 125 150 Afar Scaling Solar
3 Mekele Solar 100 120 Tigray RFP Pending
4 Humera Solar 100 120 Tigray RFP Pending
5 Welenchiti Solar 150 165 Oromia RFP Pending
6 Weranso Solar PV 150 165 Afar RFP Pending
7 Metema Solar PV 125 150 Amhara Awaiting approval
8 Hurso Solar PV 125 150 Dire Dawa Awaiting approval

Key Challenges

Following some challenges from previous solar energy investments, for example the 100 MW Metahara solar project awarded to Enel in October 2017, the Government of Ethiopia has agreed to take a more active role in the procurement process in an effort to streamline the implementation of these projects. Some of the key challenges included:

  • acquisition of land processes;
  • the lack of a “one-stop shop” service for licensing and approvals (meaning that investors in PPPs are required to obtain licences and approvals from different institutions or regulatory bodies, whereas investors outside of PPPs are able to manage this process through a single entity, the Ethiopian Investment Commission);
  • payment guarantees from Ethiopian Electric Power (EEP) for defaults under the PPA;
  • securing competitive financing;
  • converting local currency into USD or any other foreign currency; and also
  • a lack of know-how in key government stakeholder departments.
     

Key Interventions

The following specific interventions by government have also been initiated to assist projects with some of these challenges:

  • the government will facilitate the acquisition of land rights on behalf of projects. For example, the land sites for the Scaling Solar projects has been identified and the process for the transfer of land use rights has already begun;
  • the PPP Proclamation provides that restrictions in tenure of land and the bidding system will not apply to PPP projects and that a right may be created for security interests over assets, as required to source financing for PPP projects; and also
  • the forex directive, which provides for on-demand access to foreign currency for payment of external debt obligations and suppliers’ credit, will also ease access to finance for investors.

Other incentives that may be available for PPP investors, subject to negotiation and agreement with EEP (and other government departments), include:

  • compensation for change of laws specifically applicable to the infrastructure being developed or the service it provides;
  • assignability of the project agreements;
  • certain tax incentives;
  • government economic support and guarantee for the sustainability, implementation, and financial viability of the project including the provision of minimum off-take, availability payments, and cash subsidies; and lastly,
  • a free choice of dispute resolution mechanism.

 