CONSTRUCTION OF U.S.$109M KUNZVI DAM GATHERING PACE IN ZIMBABWE
Construction work at the Kunzvi Dam in Zimbabwe is gathering pace as the excavation of the dam foundation has reached an advanced stage. The project located at Goromonzi district, which is worth US$109 million is now 8% completion with more work still left to be done after stalling for two decades. The progress was made known after a site visit by officials from the Zimbabwe National Water Authority (Zinwa) and the Ministry of Local Government…