UGANDA’s PALLISA-KAMONKOLI ROAD PROJECT PROGRESS REPORT
The construction of 44km Pallisa-Kamonkoli road is currently at 45.3% completed according to the latest update from Uganda National Road Authority (UNRA).
UNRA made the statement via their social media handle that the project has been handed over by the contractor. That cummulative progress of works on the whole project is 62.35% & substantial completion is expected with in the set date of June 2021.
Project Update: A 19.94km (45.3%) completed section on Pallisa – Kamonkoli (44km) road project has been handed over by the contractor. Cummulative progress of works on the whole project is 62.35% & substantial completion is expected with in the set date of June 2021. #UNRAWorks pic.twitter.com/EeYHOYEDQT
— UNRA_UGANDA (@UNRA_UG) June 8, 2020
The project had been delay due to the heavy rainfall that occurred in December last year. Work has come to a stand still in areas where they are constructing bridges due to the rains in Elgon sub-region.